Mandan to weigh grant bid for $4.3M Phase II rebuild of downtown 1st Street NW and avenues

The Mandan City Commission on Dec. 1 will consider applying to the NDDOT Urban Grant Program for the second phase of downtown street reconstruction, estimated at $4.3 million, with the city eligible for up to 80% of eligible costs, or about $3.0 million.

By Bismarck Local Staff
Ask AI

Summarize this page with

ChatGPTClaudePerplexityGoogle AI

In short

  • The item is on the consent agenda for the 5:30 p.m. meeting at Mandan City Hall.
  • The project area was last surfaced or maintained in 1998, it says.
  • Angled parking would stay on some of the corridor, with parallel parking considered where encroachments limit space.

On Tuesday, Dec. 1, the Mandan City Commission will consider applying to the NDDOT Urban Grant Program for Phase II of the reconstruction of 1st Street NW and several avenues in the core downtown area, according to the commission's agenda packet.

The item is on the consent agenda for the 5:30 p.m. meeting at Mandan City Hall. The city engineer is listed as presenter, and the staff recommendation is to approve applying.

The Details

  • Estimated cost: about $4.3 million in total, per the staff memo prepared Nov. 17.
  • Grant share: the memo says the city would be eligible for up to 80% of the project's eligible costs, about $3.0 million. Phase I was awarded at 65%, so the memo notes partial awards are possible.
  • How it gets there: the Metropolitan Planning Organization asked for NDDOT funding applications to be submitted to it; staff says Phase II fits the program and should be a competitive application.
  • Length: the three-phase project covers about 4,500 feet of downtown streets; Phase 2 is about 1,600 feet, per the draft application.

What the Work Includes

The draft application describes a full reconstruction rather than a mill and overlay, citing deteriorated road conditions, curb, gutter and sidewalk in very poor condition, sidewalks that do not all meet ADA standards, and watermain that needs replacement. The project area was last surfaced or maintained in 1998, it says.

Plans call for concrete pavement, sidewalks rebuilt to ADA standards, curb bump-outs at 1st Street intersections to shorten pedestrian crossings, new LED lighting, landscaping and streetscape features in line with the 2019 Main Street project and the 2026 Phase 1 work on 1st Street NW. Angled parking would stay on some of the corridor, with parallel parking considered where encroachments limit space. Watermain replacement would be paid locally because it is not grant-eligible.

What It Means for Downtown Businesses

The application says closures are expected during construction because it is a full rebuild, and that the city "will coordinate with the property owners and businesses as much as possible." It also says the city would plan around the five or six summer weekends with downtown events, and that sidewalk reconstruction will run right up to the property line, with zero building setbacks in many cases.

The application cites requests to use avenue sidewalks for patron seating if improvements are made. It points to new service-oriented businesses choosing downtown, and says a retail store and a locally owned restaurant relocated to the area after the city bought long-vacant property between 4th and 6th avenues just north of Main.

Before You Go

  • The draft application attached to the memo carries older, higher numbers than the memo: it puts Phase 2 at $5.9 million and requests $3.5 million, and its cost table totals about $6.24 million, with about $3.76 million in grant funds. Its detailed cost estimate is marked prepared October 2025. The memo's $4.3 million is the packet's most recent estimate.

Sources: Mandan City Commission Dec. 1, 2026 agenda packet (pp. 1-2, 61-83); Mandan City Commission Dec. 1, 2026 preliminary agenda

Know someone who should see this?

Ask AI

Summarize this page with

ChatGPTClaudePerplexityGoogle AI

Also in Bismarck

Your town, every weekday morning

What’s on today, new local guides and stories, in one short free email.

Free. Unsubscribe any time.