A 145-lot expansion of the South Heart Terrace neighborhood on Mandan's south side goes before the Mandan Planning & Zoning Commission at 5:30 p.m. tonight, Monday, Nov. 23, in the commission room at Mandan City Hall.
The public hearing covers three requests at once for South Heart Terrace 5th Addition: a preliminary plat, a zone change and an annexation of part of the land into city limits, according to the agenda packet.
The Details
- Size: 69.41 acres in the northwest quarter of Section 3, Township 138N, Range 81W, split into seven blocks and 145 lots, one of them an existing drainage basin. The plat lists 55.91 acres in lots and 13.5 acres of dedicated right-of-way.
- Lots: From just over 10,000 square feet to nearly 36,000 square feet.
- Housing mix: Most lots would be zoned R7, the city's standard single-family district. Twenty-eight lots in Blocks 2, 3 and 4 would be zoned R3.2, which allows detached homes and duplexes. The four lots in Block 1, on the west side of 8th Avenue SW, would be zoned RM for multi-unit housing at up to 30 units per net acre.
- Annexation: A portion of the land is now zoned agricultural and outside city limits; the rest is already R7.
Streets and Utilities
The addition extends 8th, 6th and 4th avenues SW and Cobblestone Loop south from South Heart Terrace 3rd Addition. A new east-west street, Inspiration Drive, would reach the township road on the east edge and is meant to tie into the proposed Clover Grove subdivision. Staff wrote that south Mandan subdivisions have tended to be "self contained rather than providing east-west access," and that this plat addresses that concern.
8th Avenue SW would shift east and operate as a collector with limited access points, because land to the south could someday hold intensive uses such as a hotel, conference center or school, the staff report says.
Engineering staff say all lots can get water and sewer, though some in Blocks 5 and 7 would need a sewer line along the township road or through Clover Grove.
The Backstory
Part of the site was platted earlier as the 4th Addition, which was vacated. The staff report says an earlier application was recommended for denial by the Planning & Zoning Commission in April 2025 and was later tabled in fall 2025; staff had continued concerns about connectivity east to Clover Grove, and engineering staff about secondary access for fire and emergency services. The new application, received Oct. 22, adds land to the south.
What's Next
Staff recommend approval, contingent on the City Commission approving the annexation. Items to fix include a Block 7 lot with too little frontage; a development agreement will be required at final plat, and park needs will be set then.
The draft zoning ordinance lists City Commission first consideration Dec. 15 and final passage Jan. 5, 2027. The city takes emailed comments at info@cityofmandan.com before 3:30 p.m. on meeting day.