Apple Creek Road is open to traffic after roadway striping was completed, Burleigh County said in an update dated Nov. 11, 2026.
The county said all pieces of the box culvert have been placed and the channel is open, and flowable fill work is complete. Asphalt paving was completed Nov. 9, while striping was completed Nov. 11, according to the announcement.
Burleigh County said crews planned to complete seeding, minor punch-list work and final cleanup on Nov. 13, with flagging as needed. The announcement did not specify times or a project cost.
Questions may be directed to Casey Einrem at the Burleigh County Highway Department at 701-204-7748, the county said.