Apple Creek Road reopening projected for Nov. 9

Burleigh County says Apple Creek Road is projected to reopen Nov. 9, weather permitting.

By Bismarck Local Staff
Ask AI

Summarize this page with

ChatGPTClaudePerplexityGoogle AI
Editorial illustration: Apple Creek Road reopening projected for Nov. 9

In short

  • Burleigh County says Apple Creek Road is projected to reopen Nov. 9, weather permitting, as Central Specialties works on the bridge project and con...
  • The county said all pieces of the box culverts have been placed, and formwork was underway to prepare for flowable fill placement on Friday, Oct. 30.
  • Backfilling around the box culverts was scheduled for Oct. 31 and Nov. 1, according to the county’s update.

Burleigh County says Apple Creek Road is projected to reopen Nov. 9, weather permitting, as Central Specialties works on the bridge project and continues construction through weekends.

The county said all pieces of the box culverts have been placed, and formwork was underway to prepare for flowable fill placement on Friday, Oct. 30.

Backfilling around the box culverts was scheduled for Oct. 31 and Nov. 1, according to the county’s update. Riprap placement was expected to begin early the following week, with asphalt paving set to start toward the end of the week, weather permitting.

The county said topsoil and seeding are planned after paving. Its announcement also points readers to a map showing the construction area and detour.

The update was issued by the Burleigh County Highway Department. For more information, the county listed Casey Einrem at 701-204-7748 as the contact.

Know someone who should see this?

Ask AI